Before a contractor starts fitting out the shop, office or restaurant you lease: what must the fit-out agreement say about scope and drawings, price and variations, payments and retention, delay, the landlord's approval and the permits, handover and defects, and what does Saudi law decide when the contract is silent?

A practical guide for the business owner opening a branch in leased premises with nothing but a contractor's quotation: what to write before the first day of work, and what governs each point the contract leaves out.

Reviewed by Abdulaziz Sukkar, a licensed Saudi lawyer Updated 23 November 2026 12 min read

Before the contractor starts, the fit-out agreement must tie the work to signed drawings and specifications, fix a lump-sum price that changes only by a written variation order, link each payment to an inspected stage with an amount held back, set a handover date and delay compensation, require the landlord's approval and the permits before work begins, and set the handover report and the defects period. Whatever it leaves out, the Civil Transactions Law decides.

In the eyes of the law, a fit-out agreement is a contracting contract: Article 461 of the Civil Transactions Law defines contracting as a contract under which the contractor undertakes to make a thing or perform a work for a fee, without being the employer's subordinate or agent. The contracting provisions in Articles 461 to 478 fill whatever the contract leaves out, and the lease provisions in Articles 418 to 438 govern your relationship with the landlord while you change the premises. That is why a quotation alone leaves most questions to general texts that may not suit your opening date.

The latest development touching business contracts: on 13 November 2026 the Umm Al-Qura Gazette published the Commercial Transactions Law, and its Article 271 says it takes effect one hundred and eighty days after publication. Its Article 6 lists "construction contracting" among the activities it treats as commercial, but its commercial contracts part regulates commercial sale, supply sale, commercial agency and brokerage, and has no chapter on the contracting contract. The rules this guide relies on are therefore the contracting provisions of the Civil Transactions Law.

This guide does not repeat what other Sighaty guides already answer: the guide to the commercial lease and its Ejar authentication answers the clauses of the lease itself, the guide to cleaning, maintenance or security contracts answers service levels after opening, and the guide to subcontracting answers whether the contractor may hand the work to a subcontractor and whether that subcontractor can claim from you directly. This guide is from Sighaty, the platform whose templates are certified by Abdulaziz Sukkar, a licensed Saudi lawyer; its text is current to 23 November 2026, and it is general information, not legal advice on a particular case.

Get the Fit-Out AgreementP-05

What do you do before you sign with the contractor?

Turn the quotation into a written contract with the drawings, the specifications and the payment schedule attached, get the landlord's written approval before any work, and then allocate responsibility for the permits by name. These are the steps in the order that protects your opening date:

  1. Read the lease first: what it says about alterations to the premises, about when rent starts, and about what stays or is removed when the lease ends.
  2. Ask the contractor for execution drawings, a bill of quantities and material specifications, and have both of you sign them so they become part of the contract.
  3. Show the drawings to the landlord and get the landlord's written approval of them before any demolition or installation.
  4. State in the contract who obtains each licence or permit the municipality and other authorities require, and who bears any delay in it.
  5. Choose the price method, a lump sum on an agreed design or unit rates on a bill of quantities, and write the variation order procedure.
  6. Tie each payment to a stage that is inspected and approved in writing, and set the amount held back and when it is released.
  7. Write the handover date, the compensation for each day of delay and its ceiling, then the period for fixing snags at handover and the defects period.

What does the contract say about scope, drawings and materials?

The contract must describe the work through signed drawings and specifications, not a general phrase such as "full finishing", because the law binds the contractor to complete the work according to the contract's terms, and where there are no terms it binds the contractor only to accepted practice (Article 465). The difference between the two is the difference between the flooring you chose and flooring that is "acceptable by custom".

The materials may come from the contractor or from you (Article 462). If the contractor supplies them, the contractor is responsible for their meeting the agreed specifications where there are any, and otherwise must ensure they are fit for the purpose according to custom. If you supply them, such as lighting or equipment you buy yourself, the contractor must look after them with the care of an ordinary person, follow technical practice and return whatever is left (Article 463). The contractor bears the cost of machinery and tools unless agreed otherwise (Article 464).

The drawings carry legal weight beyond the contract: the Law on Implementation of the Saudi Building Code applies the code to existing buildings when they are renovated, change use, are extended or are altered (Article 2), makes compliance with the code a requirement for renovation, alteration and change-of-use permits (Article 6), requires design, supervision and execution to be under contracts with specialists holding practice licences (Article 7), and binds the designer, the contractor and the supervisor to carry out their assigned work according to the code (Article 8). So have the contract state that the contractor holds the required practice licence and will carry out the works according to the code.

Does the price change if costs rise or you ask for extra work?

If the price is a lump sum on an agreed design, the contractor may not claim any increase even if material prices or labour wages rise (Article 471, paragraph 1), and may not claim an increase for a change or addition to the design unless it is due to your fault or was made with your permission and you agreed on the increase (paragraph 2). The real protection is therefore a written variation order that sets the extra work, its price and its effect on the handover date before it is carried out.

The law provides one exception: if the contractual balance collapses because of general exceptional circumstances that could not be foreseen at contracting, the court may restore the balance by extending the time, increasing or reducing the fee, or may terminate the contract (Article 471, paragraph 3).

If the price is unit rates on a bill of quantities, and it emerges during the work that carrying out the design requires a clear overrun of the estimated quantities, the contractor must notify you at once of the expected increase, or loses the right to whatever exceeds the value of the quantities. If the overrun is substantial, you may withdraw from the contract and stop the work without delay, paying the value of what was done under the contract's terms (Article 470). And if the contract does not set the fee at all, the contractor is entitled to the market rate for the work plus the value of the materials supplied (Article 472), which is what happens when work starts on an incomplete quotation.

When do you pay, and how does retention work?

The default rule is that you pay the fee when you take delivery of the agreed work, unless agreed otherwise (Article 469, paragraph 1). If the work consists of several parts, or the fee is per unit, you pay for what has been completed after inspecting and accepting it, provided the completed part is distinct or significant within the work as a whole (paragraph 2). So if the contractor wants an advance or weekly payments, that is an agreement that must be written down.

Retention is an amount held back from each payment as security for fixing snags and defects, and then released. Because the default is payment on delivery unless agreed otherwise, the amount retained, when it is released and the condition for release are set by the contract's terms, so write them clearly. Do not put a fixed-percentage late charge on sums of money owed by either side: Article 178 allows compensation to be fixed in advance unless the obligation is a sum of money.

Ready-to-use clause • copy directly

يُصرف لكل مرحلة واردة في جدول الدفعات مستخلصها بعد أن يعاينها صاحب العمل أو مهندسه ويقر كتابةً بإنجازها وفق المخططات المعتمدة، ويُحجز من كل مستخلص المبلغ المبين في الجدول ضماناً لإصلاح الملاحظات، ويُرد المحجوز بعد انقضاء مدة ضمان العيوب دون ملاحظة قائمة.

Each stage listed in the payment schedule is paid after the employer or its engineer inspects it and confirms in writing that it was completed according to the approved drawings. The amount shown in the schedule is held back from each payment as security for fixing snags, and the amount held is released once the defects period ends with no item outstanding.

A short illustrative clause. The full certified text of the payment schedule and retention is in the Fit-Out Agreement template P-05.

What if the contractor misses your opening date?

The contractor must finish within the agreed time, and if no time is set, within the reasonable time the nature of the work requires (Article 465), and "reasonable" knows nothing of your opening date. A debtor who delays performance must compensate the harm caused by the delay unless the debtor proves it was due to a cause beyond their control (Article 171), and compensation is due only after formal notice unless there is an agreement or provision to the contrary (Article 175). Notice may be given by any means the parties agreed or any means the law sets for notification (Article 177), so write the notice method into the contract.

Because the contractor's obligation is a work and not a sum of money, compensation for each day of delay may be fixed in advance in the contract, and formal notice is not a condition for it (Article 178). But agreed compensation is not due if the contractor proves you suffered no harm at all, the court may reduce it if it was excessive or part of the obligation was performed, and may raise it to the level of the harm if the harm exceeded it through fraud or gross negligence (Article 179). So keep evidence of your harm, such as the rent you paid for the days of delay. A ceiling on the compensation is allowed within Article 173: the exemption does not cover fraud or gross negligence, and no agreement may exempt from liability for a harmful act.

If the contractor breaches the contract's terms during the work, you may give formal notice to correct the work within a reasonable time you set, and if it passes without correction you may give the work to another contractor at the first contractor's expense under Article 167, or ask for termination. You may ask for immediate termination if the defect cannot be fixed, or if the contractor is so late in starting or finishing that completion within the agreed time cannot be expected (Article 466). The parties may agree on a right to terminate without a court judgment, but that does not dispense with formal notice unless they expressly agree so (Article 108).

Ready-to-use clause • copy directly

إذا لم يُسلَّم العمل في الموعد المحدد لسبب يرجع إلى المقاول، استحق صاحب العمل عن كل يوم تأخير التعويض المبين في ملحق الأسعار، بحد أقصى مجموعه المبين فيه، ولا يمنع ذلك صاحب العمل من الفسخ وفق هذا العقد إذا تجاوز التأخير المدة المحددة في الملحق.

If the work is not handed over on the set date for a reason attributable to the contractor, the employer is entitled, for each day of delay, to the compensation stated in the price annex, up to the total ceiling stated there. This does not prevent the employer from terminating under this contract if the delay exceeds the period set in the annex.

A short illustrative clause, and the court may reduce agreed compensation under Article 179. The full certified text is in the Fit-Out Agreement template P-05.

Do you need the landlord's approval, and who obtains the permits?

Yes. A tenant may not make a change to the leased premises without the landlord's permission, unless the change is required to repair the premises and causes it no harm (Article 432), and a fit-out is usually a change, not a repair. So make the landlord's written approval of the drawings a condition for starting work in the fit-out agreement, so you do not pay the contractor for work you may be asked to stop.

The approval has a financial effect when the lease ends. If a tenant, with the landlord's permission, makes constructions or repairs for the benefit of the premises, the tenant may recover what was spent to the customary extent, while what was made for the tenant's own benefit gives no right of recovery, unless agreed otherwise in either case (Article 422). The tenant must return the premises in the condition received, except for what ordinary use entails (Article 435), and for a construction the tenant made for its own benefit with no agreement that it stays, the landlord may ask for its removal at the tenant's cost or keep it at the value Article 436 sets. So ask that the landlord's approval state what stays and what is removed when the lease ends.

As for the permits, the contract is what allocates them: write who files each licence application the municipality, Civil Defense or any other authority requires, who bears its cost, and whether the handover date is extended if a permit is delayed through no fault of the contractor. Remember that the Building Code Implementation Law makes code compliance a requirement for renovation and alteration permits (Article 6), so a design that breaches the code can hold up the permit itself. And if the fit-out is on a part you sublet, the landlord's consent to the sublease is an earlier question answered by Article 437 and template P-02.

How do you take handover, and who bears defects after it?

Take handover with a joint report that records the snags and the period to fix them, because the law requires you to take delivery promptly once the contractor has finished the work and placed it at your disposal, and if you refuse without lawful reason despite being notified, and the work is then destroyed or damaged in the contractor's hands without the contractor's fault or negligence, the contractor owes no compensation (Article 468). Before handover, if the work is destroyed or damaged for a reason beyond the contractor's control, the contractor may claim neither the fee nor the costs, unless you were at that time in breach of your duty to take delivery (Article 467).

Contracts of exchange are deemed concluded on the basis that their subject is free of defects except those custom tolerates, and a defect custom does not tolerate counts as a breach of obligation (Article 109); after formal notice you may ask for performance or termination, with compensation where warranted (Article 107). But the contracting provisions do not set a specific period for defects in fit-out work after handover, so write into the contract the defects period, how a defect is notified, the time the contractor has to fix it, and your right to have it fixed at the contractor's cost if the contractor does not.

  • A joint handover report attaching the snag list and the period to fix it.
  • A defects period starting on the report's date, after which the retention is released.
  • Handover of as-built drawings and the manufacturers' warranties for equipment and materials.
  • Third-party liability insurance for the whole period of work in premises the public visits or that adjoin other shops.

The Fit-Out Agreement template P-05 is written for the contracting provisions of the Civil Transactions Law and covers the completion period, a lump-sum or bill-of-quantities price, payments tied to approval by the employer or its engineer, retention, capped delay compensation, handover by a joint snagging report, the defects warranty, third-party liability insurance, a cure period before termination, sample approval before installation, and who is responsible for the permits; it is produced in Arabic and English, and the Arabic text prevails.

Frequently asked questions

I only have a signed quotation from the contractor. What governs what it leaves out?

The contracting provisions of the Civil Transactions Law: the reasonable time the nature of the work requires and accepted practice where no time or terms are set (Article 465), payment on delivery unless agreed otherwise (Article 469), and the market rate where no fee is set (Article 472). These rules know nothing of your opening date or your specifications, so turn the quotation into a contract before work starts.

May the contractor raise a lump-sum price because material prices went up?

No, if the price is a lump sum on an agreed design (Article 471, paragraph 1), except in general, unforeseeable exceptional circumstances in which the contract's balance collapses, where the court may restore the balance or terminate the contract (paragraph 3). Any extra work you request needs an agreement on its price (paragraph 2).

Do I pay the landlord rent during the fit-out works?

The tenant must pay rent on the agreed dates, and rent is not due for a period that passed before the premises were handed over unless the delay was the tenant's doing (Article 429). Once you receive the premises, rent runs under the lease even if the contractor is still working, which is why any rent-free fit-out period is negotiated in the lease itself, and also why every day of contractor delay costs you.

Does the Commercial Transactions Law published in November 2026 change the rules for a fit-out agreement?

The Umm Al-Qura Gazette published it on 13 November 2026, and it takes effect one hundred and eighty days after publication (Article 271). It lists "construction contracting" among commercial activities in its Article 6, but its commercial contracts part has no chapter on the contracting contract, so the contracting provisions of the Civil Transactions Law remain the reference for the points in this guide. What its general rules for traders may mean once it takes effect is a matter worth following.

May the contractor hand part of the work to another contractor?

That question is answered by Sighaty's guide on subcontracting without the client's consent. What matters for the fit-out agreement is that you state your position expressly: whether your written permission is needed before subcontracting, and that the contractor stays responsible to you for the whole work.

Certified template · P-05

The next step

This guide ends with a ready bilingual template, drafted from the statute and its regulations and reviewed by a licensed Saudi lawyer.