Can a contractor subcontract the work without the client's consent, and can the subcontractor claim payment from the client directly?

When work may be given to a subcontractor, why you stay liable to your client, when the subcontractor may claim from the client directly, and what the subcontract must settle.

Reviewed by Abdulaziz Sukkar, a licensed Saudi lawyer Updated 22 November 2026 10 min read

Yes, as a rule. Article 473 of the Civil Transactions Law lets the contractor give all or part of the work to a subcontractor, unless statutory texts, the agreement or the nature of the work require otherwise or the contractor was chosen for who he is, and the contractor stays liable to the client. The subcontractor may not claim from the client what is due to the contractor unless the contractor assigned him to the client (Article 474).

In this guide we call the party that ordered the work "the client", while the Civil Transactions Law calls it "صاحب العمل" (literally, the owner of the work). Article 461 defines a contract for work as a contract under which the contractor undertakes to make a thing or perform work for a fee without being subordinate to or an agent of صاحب العمل. So when you read Articles 473 and 474, صاحب العمل there is your client, not the employer of workers in the sense of the Labor Law.

This guide explains how to check the main contract before subcontracting, what the subcontract must carry over from your obligations, and how assignment works as a route to direct payment, then gives a checklist before signing. It covers contracts between private businesses; government projects have their own rules and are outside its scope.

Reviewed by Abdulaziz Sukkar, a licensed Saudi lawyer. Last updated 16 November 2026 (6 Jumada II 1448H).

Get the Subcontract templateC-12

Does the contractor need the client's consent before subcontracting?

The Civil Transactions Law does not require the client's consent as a general rule. The first paragraph of Article 473 states that the contractor may give the performance of all or part of the work to a subcontractor, then sets out four exceptions: where statutory texts require otherwise, where the agreement requires it, where the nature of the work requires it, or where the contractor was chosen for who he is. So if the main contract requires the client's consent or forbids subcontracting, or the client chose the contractor for his person and expertise specifically, the door to subcontracting narrows or closes, and the main contract becomes the first reference.

Government projects are governed by the government tenders and procurement rules and their own provisions on subcontracting, which are outside the scope of this guide. If your main contract is with a government body, refer to those rules and to your contract with that body, and to our guide on local content in government contracts.

  1. Read the whole main contract and look for any clause that forbids subcontracting, makes it subject to the client's written consent, or limits it to a list of contractors the client approves.
  2. Check the annexes, the scope of work and the agreed correspondence, since the consent requirement may sit in a technical annex rather than the body of the contract.
  3. Ask yourself: did the client choose you for who you are or for the expertise of a named team? If the contract names people or ties the work to your own skill, your person may be a decisive factor.
  4. Look at the nature of the work itself, since some work rests on the contractor's particular skill so that its nature requires him to perform it himself.
  5. If you find a consent clause or are unsure whether something prevents subcontracting, ask for the client's written consent before signing the subcontract, naming the subcontractor and the scope given to him.
  6. Keep the consent in the project file, since it is your evidence if a dispute later arises over whether subcontracting was allowed.

What does it mean that the contractor stays liable to the client?

The second paragraph of Article 473 states that the contractor's liability to صاحب العمل remains in place. Subcontracting does not transfer the main contract to the subcontractor and does not release the contractor from his obligations. If the subcontractor is late or makes a mistake in the part given to him, the client looks to the contractor under its contract with him, and it is for the contractor to recover from the subcontractor as the subcontract provides. That is why the subcontract is your main tool for recovering what you bear before the client because of someone else's failure.

Another aspect concerns the subcontractor's workers. Article 11 of the Labor Law, in its text as amended by Royal Decree M/46 dated 5/6/1436H, provides that if an employer entrusts any natural or legal person with carrying out any of its original work or part of it, the latter must give its workers all the rights and benefits that the original employer gives its own workers. "Employer" here means whoever employs workers in the sense of the Labor Law. In practice, the subcontract should state the subcontractor's commitment to this rule and allow you to verify it.

  • Delivery dates in the subcontract should come before your dates with the client, to leave room for review and correction.
  • Quality and acceptance standards should match what you committed to, or you may accept work from the subcontractor that the client then rejects.
  • The subcontractor's responsibility for the part given to him should be written out in detail in the subcontract, because the client will not look to him but to you.

What must the subcontract carry over from the main contract?

The subcontract must pass on to the subcontractor every obligation in the main contract that touches the part given to him: scope, deadlines, quality, confidentiality and payment timing. The practical rule is that any obligation you owe the client and do not pass on to the subcontractor stays with you alone. Follow these steps when drafting or reviewing the contract:

  1. Scope: carry over the description of the subcontracted part from the original scope of work precisely, attach the specifications and drawings, and do not settle for a general phrase such as "finishing works".
  2. Deadlines: make the interim and final delivery dates in the subcontract earlier than your dates with the client, and link any extension the client grants you to a written mechanism for a matching extension in the subcontract.
  3. Quality and acceptance: tie your acceptance from the subcontractor to the client's own standards, keep your right to reject non-conforming work and require it to be fixed, and state that your initial acceptance does not stop you from recourse if the client later rejects the work.
  4. Confidentiality: if the main contract binds you to confidentiality or to protecting the client's data, pass the same obligation on to the subcontractor and his workers, and limit what you disclose to what he needs to perform the subcontracted part.
  5. Payment timing: set the subcontractor's payment dates and the conditions for each payment clearly: for which stage, after which acceptance, and against which documents. Whether a clause tying payment to your receipt from the client (a "pay when paid" clause) will stand is a question this guide does not settle, so have a lawyer review its wording before you adopt it.
  6. The subcontractor's workers: carry over the rule in Article 11 of the Labor Law expressly, and ask for proof that the subcontractor honours his workers' rights.
  7. Further subcontracting: forbid the subcontractor from passing on what was given to him to anyone else without your written consent, so you do not lose control of the delivery chain, especially where the main contract restricts subcontracting.
Ready-to-use clause • copy directly

يلتزم مقاول الباطن، في حدود الأعمال المسندة إليه، بالالتزامات التي يتحملها المقاول تجاه صاحب العمل بموجب العقد الأصلي المرفق، بما فيها مواصفات العمل ومعايير الجودة والاستلام ومتطلبات السرية، وتسري عليه مواعيد التسليم الواردة في الملحق (أ) من هذا العقد، وهي سابقة لمواعيد العقد الأصلي.

Within the limits of the works given to him, the subcontractor shall be bound by the obligations the contractor owes صاحب العمل under the attached main contract, including the work specifications, the quality and acceptance standards and the confidentiality requirements, and the delivery dates in Annex (A) of this contract, which fall before the dates of the main contract, shall apply to him.

A short illustrative wording that does not replace the contract. The full certified text of the flow-down, payment and assignment clauses is in the Subcontract template C-12.

Can the subcontractor claim his payment from the client directly?

No, as a rule. Article 474 of the Civil Transactions Law states that the subcontractor may not claim for himself from صاحب العمل anything of what is due to the contractor, unless the contractor assigned him to صاحب العمل. The money the client owes the contractor remains the contractor's right, and the subcontractor's claim lies in the first place against the contractor who hired him.

The exception the text opens is assignment: the contractor assigns the subcontractor to the client. That makes assignment a useful negotiating tool: the subcontractor gets a closer source of payment, the contractor eases cash flow pressure, and the client knows in advance whom to pay. The conditions and form of assignment and its effect on each party's obligations are governed by the general rules of the Civil Transactions Law, which this guide does not detail, so have a lawyer review the wording before signing.

  1. Agree in the subcontract, or in a later agreement, whether assignment to the client is available and which payments or stages it covers.
  2. Review the main contract before assigning; if it restricts assigning receivables or requires the client's consent to it, obtain that consent first.
  3. Define the assigned amount precisely: which payment under the main contract, what value in riyals, and for which part of the works.
  4. Put the assignment in writing, signed by the contractor and the subcontractor.
  5. Notify the client of the assignment in writing and ask for an acknowledgment, so the client knows whom to pay and does not pay the same amount to the contractor again.
  6. Keep copies of the assignment, the acknowledgment and the proof that the works matching the assigned amount were performed, since that is what the subcontractor needs if he has to make a claim.

Checklist before signing the subcontract

Before you sign the subcontract, or agree to be the subcontractor under it, go through this list. Each item answers a question that will be asked at the first delay or payment dispute.

  • I reviewed the main contract and its annexes and found nothing that forbids subcontracting or requires consent, or I obtained the client's written consent.
  • I confirmed that I was not chosen for who I am under the main contract, or that the client agreed to subcontracting regardless.
  • The scope of the subcontracted part is carried over from the main contract with the specifications and drawings.
  • Delivery dates in the subcontract are earlier than my dates with the client, with a written extension mechanism.
  • Quality and acceptance standards match the client's, with a right to reject and require repairs.
  • Confidentiality and data protection are passed on to the subcontractor and his workers.
  • Payment dates, conditions and supporting documents are defined, and any link between payment and receipt from the client has been reviewed by a lawyer.
  • The subcontractor's commitment to his workers' rights under Article 11 of the Labor Law is written into the contract.
  • Further subcontracting is forbidden without my written consent.
  • A clear decision on assignment to the client: available or not, and for which payments.
  • A written mechanism for what happens to the subcontract if the client ends the main contract or suspends the works.
  • A copy of the relevant parts of the main contract, the subcontract, and every consent or assignment is kept in the project file.

The Subcontract template C-12 brings these clauses together in a bilingual contract you complete with smart fill in minutes. If what you buy from the other party is goods or materials rather than work he performs, the Supply Agreement C-03 may suit you better, or the Purchase Order Terms C-13 for repeat orders.

For information, the Commercial Transactions Law, issued by Royal Decree M/132 dated 21/5/1448H, was published in the official gazette Umm Al-Qura on 13 November 2026 and takes effect one hundred and eighty days after publication; this guide does not cover its provisions. This guide is general information, not legal advice on a specific dispute, and the Arabic text prevails.

Frequently asked questions

Can the client forbid subcontracting?

Yes, by agreement. Article 473 of the Civil Transactions Law makes the agreement one of the things that can require otherwise, so if the main contract forbids subcontracting or requires prior consent, the contract governs. It is clearer to write the clause expressly than to rely on interpretation.

What if the contractor subcontracts despite a clause forbidding it?

Articles 473 and 474 do not set a specific consequence for breaching a no-subcontracting clause; the consequence depends on the main contract and the facts of each case, and it is a matter for a lawyer to assess. In any event, the contractor stays liable to the client under the second paragraph of Article 473.

If the contractor does not pay the subcontractor, can the subcontractor turn to the client?

Not as a rule. Article 474 does not allow him to claim for himself from صاحب العمل anything of what is due to the contractor, unless the contractor assigned him to صاحب العمل. So his claim lies against the contractor who hired him, and the route to a direct claim is an agreed assignment.

Does responsibility for defects in the work pass to the subcontractor?

Not as far as the client is concerned: the second paragraph of Article 473 keeps the contractor's liability to صاحب العمل in place. Between the contractor and the subcontractor, it is the subcontract that sets the subcontractor's responsibility for the part given to him, which is why its quality and repair clauses must be detailed.

Is the position different on government projects?

Government projects have their own tenders and procurement rules that govern subcontracting, and this guide does not cover them. If your main contract is with a government body, refer to those rules and to your contract with that body.

Certified template · C-12

The next step

This guide ends with a ready bilingual template, drafted from the statute and its regulations and reviewed by a licensed Saudi lawyer.